Fauling Road


Zone

4

Type of Project

Dirt-to-pave

Construction Start
(or estimated start)

Anticipated May 2018 Letting

Estimated Completion

TBD

Estimated Project Budget

Approximately $900,000

Managing Agency

Berkeley County

Funding Source(s)

Berkeley County

Project Description

This project consists of paving a portion of Fauling Road from Mendel Rivers Road to near Peppermill Way. A portion of Potter Road will also be paved.

Project Status

Final design is complete and final construction plans have been prepared. Fauling Road is being combined into a single contract with four other roads and the project is being prepared for bidding by the County. Once a contractor is obtained a definitive schedule will be provided.