Murray Avenue at Yeamans Hall Road
Zone
3
Type of Project
Intersection improvements
Construction Start
(or estimated start)
April 2017
Estimated Completion
August 2017
Estimated Project Budget
$285,000
Managing Agency
Berkeley County
Funding Source(s)
Berkeley County
Project Description
Complete: This project consists of intersection improvements at the intersection of Murray Avenue at Yeamans Hall Road. The existing left turn lane on the western leg of Murray Avenue will be extended approximately 150- ft. in order to provide more left turn storage for the traffic turning onto Yeamans Hall Road heading north. Pedestrian signal improvements will also be done at the intersection.
Project Status
Complete. Ahead of schedule and under budget.