US 176 - Phase 1


1

Zone

Road widening

Type Of Project

Construction Start
(or estimated start)

Estimated Completion

TBD

Estimated Project Budget

Managing Agency

Berkeley County

Funding Source(s)

Berkeley County

Project Description

Phase 1 of this project consists of widening US 176 from two lanes to four lanes with raised concrete median from US 17 Alt. to Nexton Parkway, a distance of approximately 4.2. miles. Currently design and right-of-way plans expected by May 31, 2018 for DOT approval. The entire US 176 widening project consists of widening US 176 from US 17 Alt. to Center Line Road/Volvo Car Drive, a distance of approximately 11 miles.

Project Status

Project design is underway. Surveys, utility location, geotechnical, and environmental work is underway. Project design proceeding with a 5-lane curb and gutter section.