Back Tom Road - Phase 2
(Black Tom Extension to US 17 A)
Zone
1
Type of Project
Major resurfacing
Construction Start
(or estimated start)
April 01, 2018
Estimated Completion
Anticipated completion mid-May 2018
Estimated Project Budget
Approximately $820,000
Managing Agency
SCDOT
Funding Source(s)
Berkeley County
Project Description
Project consists of major resurfacing from Black Tom extension to US 17A, approximately 1.8 miles
Project Status
In progress. SCDOT is managing the project for Berkeley County, which is combined with two other routes that are also being resurfaced (Dr. Evans Road and Mudville Road).