SC Hwy. 6 (Pinopolis Road to CSX Railroad),
SC Hwy. 45 & Old Hwy 52


3

zone

Type of Project

Road resurfacing

Construction Start
(Or Estimated Start)

Complete

Estimated Completion

April 30, 2018

Estimated Project Budget

$12.6 million

Managing Agency

Funding Source(s)

Penny Sales Tax

Project Description

This project consists of resurfacing SC Hwy. 6 in Moncks Corner from the CSX railroad tracks in town to Pinopolis Road, SC 45 resurfacing and Old Hwy 52 for total of 18.15.

Project Status

SCDOT is managing the project for Berkeley County. This project is combined with resurfacing of SC Hwy. 45 and Old Hwy. 52 and the three projects were let together in a single contract. Bids were received on June 14, 2016 low bid of $12.56 million. Installation of concrete pedestrian ramps is complete. Once concrete patching work is complete, milling and resurfacing will be done. Contract completion date for SC 6 is April 30, 2018.