Dr. Evans Road


Zone

3

Type of Project

Major resurfacing

Construction Start
(or estimated start)

TBD

Estimated Completion

June 2018

Estimated Project Budget

$1.9 million

Managing Agency

SCDOT

Funding Source(s)

Berkeley County

Project Description

This project consists of resurfacing Dr. Evans Road from Hard Pinch Road to the end of Dr. Evans Road, a distance of approximately 5 miles.

Project Status

In Progress: SCDOT is managing the project for Berkeley County. This project is combined with two other routes in the County that are also being resurfaced (Black Tom Road and Mudville Road). Bids were received in April 2017 and the construction contract awarded to Banks Construction Company. Contract completion date for all three roads is June 30, 2018.