Volvo Interchange


Zone

1

Type of Project

Interchange construction

Construction Start
(or estimated start)

Early-2016

Estimated Completion

Mid-2019

Estimated Project Budget

$44.5 million

Managing Agency

SCDOT

Funding Source(s)

State

Project Description

SCDOT is constructing a new three-leg directional interchange along I-26 in Berkeley County,. The interchange will provide access from I-26 to the new Volvo Car Drive which leads to Camp Hall Commerce Park and the Volvo facility. The new interchange will be located along I-26 at approximate mile marker 189 which is approximately two miles east of SC 27/Ridgeville Road (exit 187) and approximately five miles west of Jedburg Road (exit 194). The proposed interchange includes both at-grade and flyover ramps.

Project Status

In progress. Foundation pile driving complete on both sides of I-26 for new bridge overpasses; bridge footings and columns complete in median; pier cap installation underway; eastbound ramps gaining elevation as mass fill operations continue; ground improvement work progressing for westbound ramps