US 52 / US 176


3

zone

Interchange improvement

Type of Project

Construction Start
(or estimated start)

Unfunded

Estimated Completion

2030

Estimated Project Budget

Managing Agency

Project Description

This project consists of evaluating an interchange at the current intersection of US 52/US 176 in Goose Creek. The project is currently funded for design to begin in year 2020 with right of way acquisition and construction unfunded at this time. A conceptual design will be generated for the purpose of coordinating with CSX Transportation, the City of Goose Creek and SCDOT.

Project Status

The project is currently in the conceptual design phase. Traffic counts are complete and a draft traffic report has been prepared. Currently coordinating with CSX for their comments on conceptual design.